home *** CD-ROM | disk | FTP | other *** search
/ Space & Astronomy / Space and Astronomy (October 1993).iso / mac / TEXT_ZIP / spacedig / V11_0 / V11_086.ZIP / V11_086
Internet Message Format  |  1991-07-08  |  3KB

  1. Return-path: <ota+space.mail-errors@andrew.cmu.edu>
  2. X-Andrew-Authenticated-as: 7997;andrew.cmu.edu;Ted Anderson
  3. Received: from beak.andrew.cmu.edu via trymail for +dist+/afs/andrew.cmu.edu/usr11/tm2b/space/space.dl@andrew.cmu.edu (->+dist+/afs/andrew.cmu.edu/usr11/tm2b/space/space.dl) (->ota+space.digests)
  4.           ID </afs/andrew.cmu.edu/usr1/ota/Mailbox/kZuWjs600VcJ0ETU4M>;
  5.           Tue, 27 Feb 90 02:27:53 -0500 (EST)
  6. Message-ID: <gZuWjVe00VcJIERk5O@andrew.cmu.edu>
  7. Reply-To: space+@Andrew.CMU.EDU
  8. From: space-request+@Andrew.CMU.EDU
  9. To: space+@Andrew.CMU.EDU
  10. Date: Tue, 27 Feb 90 02:27:30 -0500 (EST)
  11. Subject: SPACE Digest V11 #86
  12.  
  13. SPACE Digest                                      Volume 11 : Issue 86
  14.  
  15. Today's Topics:
  16.                  LOG
  17.            Payload Status for 02/26/90 (Forwarded)
  18. ----------------------------------------------------------------------
  19.  
  20. Date:          Mon, 26 Feb 90 17:04:22 LOCAL
  21. From: COP90187%UCF1VM.BITNET@mitvma.mit.edu
  22. Mmdf-Warning:  Parse error in original version of preceding line at lcs.mit.edu
  23. Subject:       LOG
  24.  
  25. qq
  26.  
  27. ------------------------------
  28.  
  29. Date: 26 Feb 90 21:59:38 GMT
  30. From: trident.arc.nasa.gov!yee@ames.arc.nasa.gov  (Peter E. Yee)
  31. Subject: Payload Status for 02/26/90 (Forwarded)
  32.  
  33. Daily Status/KSC Payload Management and Operations 02-26-90
  34.        
  35.          
  36.  
  37. - STS-31R HST (at VPF) -
  38.  
  39. On Friday access was removed along with aft shroud closeout.   
  40. On Saturday solar array closeout was started.  Today the GSFC                                           
  41. CTV will be disconnected, the HGA coupler will be removed,
  42. and the HST potentiometer will be replaced.
  43.  
  44.  
  45. - STS-32R SYNCOM/LDEF (at SAEF-2)
  46.        
  47. LDEF deintegration continues.          
  48.        
  49.  
  50. - STS-35 ASTRO-1/BBXRT (at O&C) -
  51.         
  52. BBXRT clearance checks were worked yesterday and will continue
  53. today, along with velcro patch installations, and payload   
  54. envelope clearance checks.
  55.  
  56.  
  57. - STS-40 SLS-1 (at O&C) -
  58.         
  59. The systems test was active Friday and will continue today.      
  60. Experiment functional checks will also continue today.  On 
  61. Saturday the I/O unit was changed out, cable isolation checks
  62. were performed, and pyro control and caution and warning panels
  63. were removed.  These panels will be reinstated today. 
  64.  
  65.  
  66. - STS-42 IML (at O&C) -
  67.       
  68. Staging activities were performed on racks 4 and 8 Friday.  On
  69. Saturday staging was performed on racks 3, 9, and 11.  Today     
  70. racks 7 and 11 staging operations will be performed.
  71.  
  72.  
  73. - STS-45 Atlas-1 (at o&C) -
  74.  
  75. Pallet keel installation and orthogrid hardpoint installation 
  76. operations were worked Friday.  Today pallets 1 and 2 will be
  77. repositioned on the mid-east rails.                                                         
  78.  
  79.  
  80. - STS-46 TSS-1 (at O&C) - 
  81.  
  82. PPCU checkout was worked Friday.  No scheduled activity for
  83. today.
  84.  
  85. ------------------------------